Work on Mid-Continent Railway Museum’s Chicago & North Western #1385 locomotive during the month of May has consisted of stay installation, stay installation, and more stay installation. With over 900 staybolts to be applied, this process represents one of the more time-intensive portions of the new boiler production. Each weld must be made with great care and precision to avoid leaks and ensure proper strength when the boiler is under operating pressure.
Continental Fabricator’s Tom G. peered into the belly of the beast on May 29th to take these photos of stay installation progress on the inside of 1385’s firebox.
- View of the interior of the 1385’s firebox on the fireman’s side. May 29, 2019. Photo courtesy Continental Fabricators.
- View of the interior of the 1385’s firebox looking toward the front of the boiler. May 29, 2019. Photo courtesy Continental Fabricators.
- View of the interior of the 1385’s firebox on the engineer’s side. May 29, 2019. Photo courtesy Continental Fabricators.