EJ&S #2 Restoration Update – June 17, 2019
In the May work session we decided to remove the west side letter board, siding above the window sill and the window sill. Work was then started on fabricating new window sill material.
During the June 14 and 15th work session work on the window sill was completed. This included fastening an inner trim piece to the sill and then attaching the sill to the belt rail. The next steps include installing new siding above the window sill and re-installing the top fascia and letter board.
Peter B.
Restoration Department